Deep Excavation Works for Two Inspection Shafts for the Ismailia Tunnels.jpg

Deep Excavation Works
for Two Inspection Shafts
for the Ismailia Tunnels under Suez canal

Main contractor: Petrojet Company.

Project Manager: Engineering Authority for the Armed Forces.

Consultant: CDM SMITH.

Project Overview:

​

The project consists of two car tunnels under the new and old Suez Canal.

Our Scope of Work:

​

Excavation and dredging in the presence of underground water for 7 maintenance wells up to a depth of 7 m from the surface of the earth, including drilling for a quantity of sand, stone, and mud soil until reaching the required depth using a crane with heavy clamshell and Toyo dredger pump.

Project Duration: Nov. 2016 – Apr. 2017.

Facts

Owner

Petrojet Company

Project Type

Dredging Works

Duration

(6 months)