Shore Protection for Port Said, East of El Gamil Airport

Construction of 14 Groins distributed along the beach at spacing of 175 m and extended inside the sea with varying lengths from 60 m to 120 m.

The works include the following :

-Supply and install of 36,000 m2 geotextile.
-Supply and install of 91,000 tons of rocks.
-Supply and install of 1,900 concrete dolosse.
-Sand backfilling of 350,000 m3

القوة بالأرقام

صاحب

The General Authority for Shores Protection

نوع المشروع

Ports & Marine works

مدة

Mar. 2011 - Feb. 2013