top of page

West Nile Delta Natural Gas Station Motobus D3.

The works were carried out under the full supervision of and compliance with HSE measures and requirements by BP including full health inspection of all employees and laborers, fixed truck speed under monitoring system (VDR). Our scope of work included the supply, installation, and compaction of clean sand for 373,000 m3.

The works were carried out under the full supervision of and compliance with HSE measures and requirements by BP including full health inspection of all employees and laborers, fixed truck speed under monitoring system (VDR). Our scope of work included the supply, installation, and compaction of clean sand for 373,000 m3.

Facts

Owner

Egyptian Natural Gas Holding Company.

Project Type

Earth Works

Duration

Apr. 2013 - Nov. 2013

Project Gallery

bottom of page