Project Overview:

The earthworks included excavation of 620,000m3 for an area of 79,000 m2 to depths of up to 14 m and shifting the excavated materials to the designated dumping area.

Strict HSE measures were applied to ensure safety of people, equipment, and vehicles working on steep slopes under pressing  time constrain (90 days, single shifts only) with productivity of 12,000 m3 per day.