top of page
Container Terminal in East Port-Said Port.jpg

Container Terminal in East Port Said Seaport
Dewatering, Excavation, Backfilling & Compaction

Owner: Suez Canal Container Terminal (SCCT).

Consultants: PACER & Royal Haskoning.

​

Project Overview:

​

The project included the construction of the terminal yards of 2,400 m of quay wall split into two stages (1,200 m in each stage) with container terminals of 500 m width and an overall length of 2,400 m. The two stages were split into several contracts and phases of execution. We completed the project in collaboration with several contracts either as the main contractor or as a subcontractor for ARCHIRODON Constructions Overseas Co. China Harbor Engineering Company Egypt Ltd. (CHEC) and the Petroleum Projects & Technical Consulting Company (Petrojet).

Our Scope of Work:
 

In the First Stage:
*With ARCHIRODON Include:
The excavating & dumping of 450,000 m3 and backfilling & compaction of 600,000 m3.
*As the Main Contractor, we completed the construction of the following buildings;
- Steel shed area and service building of steel skeleton including reinforced concrete footing and all finishing works, wire mesh fence and infrastructure works including water, drainage, and firefighting utilities, manholes, pump house, communication & electric utilities, and fire alarm system.

In the Second Stage:
*With China Harbor include:
Soil backfilling for sea pockets at up to -17 CD water depth, installation of a long silt screen, removal of old protection, installation of underwater sandbags at -17 CD water, and installation of underwater geotextiles and sandbags above to fix geotextiles & dewatering & excavation of 158,000 m3 of soil 6.5 m deep.

​

*With Petrojet co:

The work included excavation with dewatering & dumping of 1,300,000 m3, backfilling & compaction of 700,000 m3, sub-base paving layer, sand cement concrete paving layer, and heavy-duty interlock laying blocks.

​

*As a Main Contractor:
We completed the construction of the steel shed area and service building of the steel skeleton, including reinforced concrete footing and all finishing works, wire mesh fence, and infrastructure works, including water, drainage, and firefighting utilities, manholes, pump house, communication & electric utilities, and fire alarm system.

Project Duration: 2004 – 2012.

Facts

Owner

Suez Canal Container Terminal (SCCT)

Project Type

Infrastructure Works

Duration

(96 months)

bottom of page