Construction of The System That Carries Water From Bahr Al-Baqar Drain.jpg

The System That Carries Water From Bahr Al-Baqar Drain
To The Treatment Plant
In East Of The Suez Canal

Owner: Ministry of Water Resources and Irrigation.

Consultant: ACE Moharram-Bakhoum.

Project Overview:

A reservation bridge is constructed on the old bank at Quantum 27: The work includes making a diversion to the old bank’s path, hammering metal curtains to support the sides of drilling, carrying out concrete piles of 80 cm in diameter by rotary drilling with a length of 4,000 m and drilling with drying and making foundations, mules and bridges for the arch of reinforced concrete With a quantity of about 7,500 m3, the bridge includes 7 holes 4 m in width and equipped with metal gates that work automatically and manually and the necessary cranes for maintenance.

The arch was constructed at 17.55 m. The work includes the implementation of concrete piles of 80 cm in diameter by rotary drilling of a length of about 2,800 m and drilling with drying and making the foundations, mules, and bridge of the bridge of reinforced concrete with an amount of about 3500 m3 and the bridge includes 4 holes with a width of 4 m and is equipped with metal gates They operate automatically and manually, and the cranes are required for maintenance.

The mouth of the bridge is constructed with a weir at a quantity of 6,500 m3. The work includes the implementation of concrete piles with a diameter of 80 cm by rotary drilling of a length of about 4,000 m and drilling with drying and making the foundations, mules, and bridges for the bridge of reinforced concrete with an amount of about 6,200 m3 and the work of the weirs to reduce the level of the drain bottom from -4.0 m to -7.5 m. The bridge includes 5 holes with a width of 4 m. It is equipped with metal gates that work automatically and manually and the necessary cranes for maintenance.

Three Waste Water Canal Regulating Penstock stations, their main purpose is to regulate and control the flow of water ingress to the giant wastewater treatment plant located East of the Suez Canal. The scope was designed and built (Turnkey) and the challenge was that required double penstocks were advanced and had never been constructed in Egypt before, they could fully close the canal in 18 minutes rather than 1 hour of the conventional penstocks.

Project Duration: Jan. 2020 - Jan. 2021.

Facts

Owner

Ministry of Water Resources and Irrigation.

Project Type

Infrastructure Works

Duration

(12 months)

Project Gallery